10/09/2009
Olympic Park Clean-Up On Track As 'Big Build' Ramps Up
The clean-up of the 2.5km2 Olympic Park, much of it contaminated through decades of industrial use, is almost complete and on track to beat its tough sustainability targets.
The unprecedented clean-up began three years ago and has enabled construction to start on or ahead of schedule on all of the permanent Olympic Park venues. The 'big build' is now ramping up with venues coming out of the ground and work underway on 21 bridges, roads, a new energy centre and network and other infrastructure for the area in legacy.
ODA Director of Infrastructure and Utilities Simon Wright said: "Delivering one of the UK's most complex and greenest clean-up operations on time and on budget is a major milestone. It has ensured that the ‘big build’ is on track by creating, from mainly contaminated land, the foundation for the venues, parklands and homes that will transform this part of east London for the Games and legacy.
"We have worked closely with the regulatory bodies and local authorities while cleaning more than one million tonnes of contaminated material to protect the health and safety of the workforce, public and future generations that will live, work and play on and around the Olympic Park."
The cleaning and clearing of the Olympic Park utilised sustainable techniques to recycle and reuse over ninety per cent of the demolition material and 80% of soil on site. This significantly reduced lorry journeys in the local area as only a minimal amount of contaminated material was taken to landfill sites.
(CD/KMcA)
The unprecedented clean-up began three years ago and has enabled construction to start on or ahead of schedule on all of the permanent Olympic Park venues. The 'big build' is now ramping up with venues coming out of the ground and work underway on 21 bridges, roads, a new energy centre and network and other infrastructure for the area in legacy.
ODA Director of Infrastructure and Utilities Simon Wright said: "Delivering one of the UK's most complex and greenest clean-up operations on time and on budget is a major milestone. It has ensured that the ‘big build’ is on track by creating, from mainly contaminated land, the foundation for the venues, parklands and homes that will transform this part of east London for the Games and legacy.
"We have worked closely with the regulatory bodies and local authorities while cleaning more than one million tonnes of contaminated material to protect the health and safety of the workforce, public and future generations that will live, work and play on and around the Olympic Park."
The cleaning and clearing of the Olympic Park utilised sustainable techniques to recycle and reuse over ninety per cent of the demolition material and 80% of soil on site. This significantly reduced lorry journeys in the local area as only a minimal amount of contaminated material was taken to landfill sites.
(CD/KMcA)
Related UK National News Stories
Click here for the latest headlines.
18 May 2011
First Olympic Torch Relay Locations Announced
From Lands End to London via all the nations and regions of the UK, the first locations on the London 2012 Olympic Torch Relay route have been announced.
First Olympic Torch Relay Locations Announced
From Lands End to London via all the nations and regions of the UK, the first locations on the London 2012 Olympic Torch Relay route have been announced.
06 January 2014
Work Continues For Olympic Park Transformation
Balfour Beatty has been appointed as lead contractor to carry out works to the stadium in Queen Elizabeth Olympic Park.
Work Continues For Olympic Park Transformation
Balfour Beatty has been appointed as lead contractor to carry out works to the stadium in Queen Elizabeth Olympic Park.
13 October 2011
PM Presents Olympic Velodrome's Award
The London 2012 Olympic Velodrome has won an award - some nine months before the cycling begins. On Thursday it emerged that the Velodrome, designed by Hopkins Architects on behalf of the Olympic Delivery Authority (ODA), had been awarded the Prime Minister's Better Public Award at a ceremony in London.
PM Presents Olympic Velodrome's Award
The London 2012 Olympic Velodrome has won an award - some nine months before the cycling begins. On Thursday it emerged that the Velodrome, designed by Hopkins Architects on behalf of the Olympic Delivery Authority (ODA), had been awarded the Prime Minister's Better Public Award at a ceremony in London.
05 August 2011
Public Name New Neighbourhoods In Olympic Park
Five new residential areas that will be built on the future Queen Elizabeth Olympic Park have been named following a public competition. Almost 2,000 people submitted their suggestions to the Olympic Park Legacy Company, inspired by factors such as the future design for the area, its history or the Games themselves.
Public Name New Neighbourhoods In Olympic Park
Five new residential areas that will be built on the future Queen Elizabeth Olympic Park have been named following a public competition. Almost 2,000 people submitted their suggestions to the Olympic Park Legacy Company, inspired by factors such as the future design for the area, its history or the Games themselves.
19 August 2010
Bidding Begins For Olympic Stadium
Premier league club West Ham has six weeks to finalise its plans as the bidding process for the Olympic Stadium begins. American sports and entertainment giant, AEG, who runs the former Millennium Dome site are also believed to be potential investors.
Bidding Begins For Olympic Stadium
Premier league club West Ham has six weeks to finalise its plans as the bidding process for the Olympic Stadium begins. American sports and entertainment giant, AEG, who runs the former Millennium Dome site are also believed to be potential investors.
-
Northern Ireland WeatherToday:A chilly start with a widespread frost and some freezing fog, any freezing fog slow to clear. Otherwise bright with sunny spells and coastal showers. Light winds. Maximum temperature 6 °C.Tonight:Coastal showers dying out with a widespread frost developing along with freezing fog, which could become extensive. Winds remaining light. Minimum temperature -3 °C.