10/11/2004
MoD rapped over its handling of defence projects
The way in which the MoD buys and develops defence equipment has come under fire in a new National Audit Office (NAO) report published today.
The MoD came in for criticism after the NAO found that that, in the last year, costs on the MoD’s 20 biggest equipment projects had increased by £1.7 billion. The audit office also found that on average the projects were delayed by three months.
The total cost of the projects is now expected to reach £50 billion, which is 14% higher than originally planned.
The NAO said that historic problems with defence procurement were not being dealt with properly, and it expected to see further problems arising with these projects in the future.
Despite the development of a new procurement strategy, the Smart Acquisition system, the report found "little evidence that acquisition has been improving".
"Many problems can be traced to the fact that the MoD has not spent enough time and resources in the assessment phase. Projects less than halfway through their procurement are already expected to be delivered later or to cost more than approved. The 15 most recent projects are moving rapidly towards their ‘not to be exceeded’ approvals and six have already breached them," the report found.
As the £1.7 billion in overruns was less than the £3.1 billion reported by the NAO last year, Sir John offered his support to the MoD’s recent efforts to improve its performance – but he warned that all parts of the department needed to work together.
Sir John said: "There must be greater certainty as to when equipment will be ready for service and there must be greater control of costs. If not, some capabilities may have to be foregone or delayed to compensate for rising costs.
"It is of particular concern that newer projects are already showing increases. We are working with the MoD and industry to identify wider good practice, and I fully support the renewed efforts by the MoD to improve their performance. These efforts are as important as ever."
The MoD said today that while it was "disappointed" at the huge costs increases, a sizeable amount of the £1.7 billion overrun was down to problems associated with some older 'legacy' projects such as the Nimrod surveillance aircraft and the Brimstone anti-armour missile system.
The results also reflected the MoD's deliberate attempt to "flush out remaining problems," it said.
Lord Bach, Minister for Defence Procurement, said: "I am determined that the changes made as a result of the review of Smart Acquisition will make a significant impact on the performance of the DPA and the Department as a whole."
(gmcg/sp)
The MoD came in for criticism after the NAO found that that, in the last year, costs on the MoD’s 20 biggest equipment projects had increased by £1.7 billion. The audit office also found that on average the projects were delayed by three months.
The total cost of the projects is now expected to reach £50 billion, which is 14% higher than originally planned.
The NAO said that historic problems with defence procurement were not being dealt with properly, and it expected to see further problems arising with these projects in the future.
Despite the development of a new procurement strategy, the Smart Acquisition system, the report found "little evidence that acquisition has been improving".
"Many problems can be traced to the fact that the MoD has not spent enough time and resources in the assessment phase. Projects less than halfway through their procurement are already expected to be delivered later or to cost more than approved. The 15 most recent projects are moving rapidly towards their ‘not to be exceeded’ approvals and six have already breached them," the report found.
As the £1.7 billion in overruns was less than the £3.1 billion reported by the NAO last year, Sir John offered his support to the MoD’s recent efforts to improve its performance – but he warned that all parts of the department needed to work together.
Sir John said: "There must be greater certainty as to when equipment will be ready for service and there must be greater control of costs. If not, some capabilities may have to be foregone or delayed to compensate for rising costs.
"It is of particular concern that newer projects are already showing increases. We are working with the MoD and industry to identify wider good practice, and I fully support the renewed efforts by the MoD to improve their performance. These efforts are as important as ever."
The MoD said today that while it was "disappointed" at the huge costs increases, a sizeable amount of the £1.7 billion overrun was down to problems associated with some older 'legacy' projects such as the Nimrod surveillance aircraft and the Brimstone anti-armour missile system.
The results also reflected the MoD's deliberate attempt to "flush out remaining problems," it said.
Lord Bach, Minister for Defence Procurement, said: "I am determined that the changes made as a result of the review of Smart Acquisition will make a significant impact on the performance of the DPA and the Department as a whole."
(gmcg/sp)
Related UK National News Stories
Click here for the latest headlines.
23 January 2004
£3bn overspend identified in MoD equipment projects
Britain's overspend on its defence projects topped £3 billion last year, more than 6% above their approved costs, according to a National Audit Office (NAO) report published today.
£3bn overspend identified in MoD equipment projects
Britain's overspend on its defence projects topped £3 billion last year, more than 6% above their approved costs, according to a National Audit Office (NAO) report published today.
25 November 2005
MoD faces overspends on projects
The Ministry of Defence is still facing overspends and delays on projects, a new report has revealed. A report on the top 20 defence equipments projects, by the National Audit Office, found that the forecast cost had actually decreased by £700 million, but that each project was delayed by an average of two and a half months.
MoD faces overspends on projects
The Ministry of Defence is still facing overspends and delays on projects, a new report has revealed. A report on the top 20 defence equipments projects, by the National Audit Office, found that the forecast cost had actually decreased by £700 million, but that each project was delayed by an average of two and a half months.
18 March 2005
Helicopter shortage predicted for armed forces
A report by MPs has warned that the UK's armed forces face an "alarming" shortage of battlefield helicopters. The Public Accounts Committee's report said that the crisis was worsened by the purchase of eight Chinook helicopters, at a cost of £259 million, which have remained grounded.
Helicopter shortage predicted for armed forces
A report by MPs has warned that the UK's armed forces face an "alarming" shortage of battlefield helicopters. The Public Accounts Committee's report said that the crisis was worsened by the purchase of eight Chinook helicopters, at a cost of £259 million, which have remained grounded.
23 April 2014
Eight Renewable Energy Projects Approved
Plans for eight major renewable energy projects have been approved by the government as part of energy measures, expected to generate enough clean power for three million homes, support 8,500 new jobs and attract more than £12bn in private investment.
Eight Renewable Energy Projects Approved
Plans for eight major renewable energy projects have been approved by the government as part of energy measures, expected to generate enough clean power for three million homes, support 8,500 new jobs and attract more than £12bn in private investment.
19 August 2013
Whitehall War Office To Be Sold
A Ministry of Defence War Office building in Whitehall is to be sold to support "Defence priorities," it has been announced. The Old War Office was built in 1902 for the Imperial General Staff and was a focal point throughout the major conflicts of the 20th century. It housed numerous secretaries of state, including Winston Churchill.
Whitehall War Office To Be Sold
A Ministry of Defence War Office building in Whitehall is to be sold to support "Defence priorities," it has been announced. The Old War Office was built in 1902 for the Imperial General Staff and was a focal point throughout the major conflicts of the 20th century. It housed numerous secretaries of state, including Winston Churchill.
-
Northern Ireland WeatherToday:A showery start with outbreaks most frequent north of Lough Neagh and through the morning, before dwindling during the afternoon as the northwest breezes ease and brighter spells of weak sunshine prosper. Maximum temperature 8 °C.Tonight:A dry night, save for a few light showers around the coasts, with prolonged clear spells and light winds bringing a frosty dawn for many in central and southern parts. Minimum temperature -3 °C.