25/11/2005
MoD faces overspends on projects
The Ministry of Defence is still facing overspends and delays on projects, a new report has revealed.
A report on the top 20 defence equipments projects, by the National Audit Office, found that the forecast cost had actually decreased by £700 million, but that each project was delayed by an average of two and a half months.
The NAO said that the total forecast cost for 19 projects – not including the cost of the Eurofighter project, now called Typhoon, which is “commercially sensitive” – is £29 billion – 10% higher then the expected cost of approval.
The total delay for the projects was 375 months later than expected when approved, averaging at around 20 months per project.
The report said that the delays were mainly due to technical problems in three projects – CIP, which covers a number of software and hardware systems building on the Bowman communications project; Nimrod and ASTOR (Airborne Stand-Off Radar).
The NAO reported that timescales on 14 of the projects had not changed in the last year.
The report said that the decrease in the forecast cost was mainly due to changing requirements or reducing the quantity or capability of the equipment.
The most significant decreases of this kind were for Future Joint Combat Aircraft, the NAO said, where the MoD had removed provisions for extra capabilities, such as for weapons that were due to be added later. A more cost effective Helmet Mounted Display System was also found and the combination of these and other measures led to a reduction of £428 million, the NAO said.
The Sting Ray Torpedo Life Extension and Beyond Visual Range Air-to-Air Missile also had significant decreases in forecast costs.
The NAO said that the MoD had not spent enough time or resources in the past to predict how much projects would cost and how long they would take. However, the report found that this had improved, although greater clarity was needed
Sir John Bourn, head of the NAO, said:” The decrease in the forecast costs is a positive sign that the MOD is starting to bring its equipment programme under control. However, it is too early to judge whether this is the start of a sustained improvement in the MOD’s project management.”
(KMcA/SP)
A report on the top 20 defence equipments projects, by the National Audit Office, found that the forecast cost had actually decreased by £700 million, but that each project was delayed by an average of two and a half months.
The NAO said that the total forecast cost for 19 projects – not including the cost of the Eurofighter project, now called Typhoon, which is “commercially sensitive” – is £29 billion – 10% higher then the expected cost of approval.
The total delay for the projects was 375 months later than expected when approved, averaging at around 20 months per project.
The report said that the delays were mainly due to technical problems in three projects – CIP, which covers a number of software and hardware systems building on the Bowman communications project; Nimrod and ASTOR (Airborne Stand-Off Radar).
The NAO reported that timescales on 14 of the projects had not changed in the last year.
The report said that the decrease in the forecast cost was mainly due to changing requirements or reducing the quantity or capability of the equipment.
The most significant decreases of this kind were for Future Joint Combat Aircraft, the NAO said, where the MoD had removed provisions for extra capabilities, such as for weapons that were due to be added later. A more cost effective Helmet Mounted Display System was also found and the combination of these and other measures led to a reduction of £428 million, the NAO said.
The Sting Ray Torpedo Life Extension and Beyond Visual Range Air-to-Air Missile also had significant decreases in forecast costs.
The NAO said that the MoD had not spent enough time or resources in the past to predict how much projects would cost and how long they would take. However, the report found that this had improved, although greater clarity was needed
Sir John Bourn, head of the NAO, said:” The decrease in the forecast costs is a positive sign that the MOD is starting to bring its equipment programme under control. However, it is too early to judge whether this is the start of a sustained improvement in the MOD’s project management.”
(KMcA/SP)
Related UK National News Stories
Click here for the latest headlines.
10 November 2004
MoD rapped over its handling of defence projects
The way in which the MoD buys and develops defence equipment has come under fire in a new National Audit Office (NAO) report published today. The MoD came in for criticism after the NAO found that that, in the last year, costs on the MoD’s 20 biggest equipment projects had increased by £1.7 billion.
MoD rapped over its handling of defence projects
The way in which the MoD buys and develops defence equipment has come under fire in a new National Audit Office (NAO) report published today. The MoD came in for criticism after the NAO found that that, in the last year, costs on the MoD’s 20 biggest equipment projects had increased by £1.7 billion.
10 December 2012
Gold Heist Gang Jailed
Six members of a gang that ran a million pound gold and silver bullion heist in Belgium were jailed for more than 23 years today on Friday 8 December 2012.
Gold Heist Gang Jailed
Six members of a gang that ran a million pound gold and silver bullion heist in Belgium were jailed for more than 23 years today on Friday 8 December 2012.
23 January 2004
£3bn overspend identified in MoD equipment projects
Britain's overspend on its defence projects topped £3 billion last year, more than 6% above their approved costs, according to a National Audit Office (NAO) report published today.
£3bn overspend identified in MoD equipment projects
Britain's overspend on its defence projects topped £3 billion last year, more than 6% above their approved costs, according to a National Audit Office (NAO) report published today.
22 November 2011
Energy Reform 'Watchdog' Needed
A business lobby group, the Forum of Private Business has warned that Ofgem's shake-up of the small business energy market lacks a dedicated watchdog and could undermine the proposed reforms.
Energy Reform 'Watchdog' Needed
A business lobby group, the Forum of Private Business has warned that Ofgem's shake-up of the small business energy market lacks a dedicated watchdog and could undermine the proposed reforms.
24 August 2005
Basic bank accounts failing poorest people
Basic bank accounts are failing to meet the needs of many of the UK’s poorest people, a new survey has reported.
Basic bank accounts failing poorest people
Basic bank accounts are failing to meet the needs of many of the UK’s poorest people, a new survey has reported.
-
Northern Ireland WeatherToday:A showery start with outbreaks most frequent north of Lough Neagh and through the morning, before dwindling during the afternoon as the northwest breezes ease and brighter spells of weak sunshine prosper. Maximum temperature 8 °C.Tonight:A dry night, save for a few light showers around the coasts, with prolonged clear spells and light winds bringing a frosty dawn for many in central and southern parts. Minimum temperature -3 °C.